SINGARENI’S COAL PUZZLE
BIZ MASALA | INVESTIGATIVE
SPECIAL
Production is falling. Contractors are under scrutiny. And Telangana is searching for answers.
How
mining delays, historical audit findings and coal-transport challenges raise
questions about the state’s fuel-supply strategy
BY MURTHY ASR • BIZ MASALA

Hero image: AI-generated editorial illustration
of a coal mine, freight train and thermal power complex; not a documentary
photograph.
THE CENTRAL QUESTION
Why
did SCCL’s production fall sharply in 2025–26, what do its own records say
about contractor and project delays, and has Telangana demonstrated that its
coal-supply strategy offers the best value for electricity consumers?
The paradox of a coal-producing state
Telangana is home to Singareni Collieries
Company Limited (SCCL), an established coal producer. Yet official statistics
show production falling to 58 million tonnes in 2025–26 from 69.01 million
tonnes in 2024–25—a decline of about 16%.
The answer may not lie in one failure.
Mining operations, contractor performance, transport infrastructure, coal
quality and power-sector finances can interact. Each calls for a different
remedy. Importing coal may address a shortage of a particular grade, but it
will not automatically fix delayed mine development or inadequate logistics.
Production and dispatches: two different signals

Source: SCCL official production statistics.
Production and dispatches are separate measures; the gap requires stock and
movement reconciliation.
|
Financial year |
Production (Mt) |
Dispatches (Mt) |
|
2021–22 |
65.02 |
65.53 |
|
2022–23 |
67.14 |
66.69 |
|
2023–24 |
70.02 |
69.86 |
|
2024–25 |
69.01 |
65.23 |
|
2025–26 |
58.00 |
62.07 |
Production fell about 16% in 2025–26, while
dispatches fell about 4.8%. This divergence is a lead, not a conclusion:
opening and closing stocks, timing, coal grade and other operational factors
need to be reconciled.

Section image: AI-generated illustration of
overburden removal and heavy equipment; not an actual SCCL site photograph.
1. When contractors become a production constraint
SCCL’s February 2026 performance report
recorded coal production of 52.84 million tonnes against a cumulative target of
64.95 million tonnes for April 2025 to February 2026. Contractor-performed
overburden removal—the excavation needed to expose coal seams—was also
substantially below target.

SCCL performance against cumulative targets
through February 2026. Percentages are calculated from company-report figures.
|
Operational indicator |
Target |
Actual |
Achievement |
|
Coal production |
64.95 Mt |
52.84 Mt |
81.4% |
|
Contractor overburden removal |
406.04 million m³ |
287.33 million m³ |
70.8% |
|
Total overburden
removal |
455.04 million
m³ |
331.29 million
m³ |
72.8% |
The company attributed approximately 76% of
the production loss recorded in February to poor performance by some
overburden-removal contractors and delays in awarding new contracts. It also
cited delayed execution of new projects, shortages of working places and
adverse geological or mining conditions.
This does not establish that contractors
alone caused the annual decline. It does establish that SCCL itself identified
contractor and project delays as major factors in at least one critical month.
Were contracts awarded on time? Did contractors deploy adequate equipment? Were
penalties and performance obligations enforced? How much production was lost,
mine by mine?

Section image: AI-generated illustration of
coal logistics and freight transport; not a documentary image of a specific
railway or mine.
2. The CAG had already identified weaknesses
The Comptroller and Auditor General’s
compliance audit examined SCCL’s overburden-removal, coal-transportation and
stowing-material contracts, principally for 2018–19 to 2022–23. It identified
₹251.05 crore in avoidable expenditure associated with deficiencies in
safeguards governing equipment deployment and another ₹74.19 crore associated
with delayed enforcement of contractual terms.
These are historical audit findings; they
do not prove that the same deficiencies caused the 2025–26 production
shortfall. The report indicates that SCCL changed a contractual provision
relating to equipment deployment for new contracts from August 2023; the
precise scope and implementation should be checked against the detailed audit
discussion and subsequent contract documents. The next question is whether the
change worked, what amounts were recovered, and whether subsequent contracts
improved performance.
Important
distinction: the ₹251.05 crore and ₹74.19 crore
figures are separate CAG findings. They should not be presented as proven
current losses or added to other audit amounts without checking their
definitions and overlap.
3. Naini: coal reserves are not the same as coal delivered
The Ministry of Coal’s 2025–26 annual
report said SCCL’s Naini coal block in Odisha began production in July 2025 and
had produced about 80,000 tonnes through December 2025. A later SCCL February
2026 report appears to record cumulative production of approximately 78,000
tonnes against a target of 3.5 million tonnes through February. The figures are
not directly consistent on their face: the reporting periods differ, and the
later figure is lower than the earlier reported total. The underlying tables, reporting
definitions and any revisions must therefore be reconciled before the size of
the shortfall is stated definitively.
Even allowing for the need to reconcile
those figures, the reported output is far below the stated target and warrants
explanation. The available information does not establish that transportation
alone was responsible. Mine development, production capacity, coal quality,
reporting periods and logistics all need examination. A coal block’s value
depends on whether coal can be extracted and delivered reliably at a
competitive cost.

Section image: AI-generated editorial
illustration of a thermal power complex and coal handling; not a photograph of
Yadadri or another named plant.
4. Yadadri and the procurement question
SCCL’s February 2026 report recorded
Yadadri Thermal Power Station coal off-take of 41.40 lakh tonnes against a
cumulative target of 72.48 lakh tonnes through February—about 57.1%
achievement. This is a gap against the recorded target, not proof of an equivalent
shortage of fuel at the plant.
The Telangana government has said Yadadri
requires G-9 grade coal and that suitable supplies are not readily available
from Singareni. That claim should be tested against the plant’s technical
specifications, mine-wise grade availability, blending options, actual stocks
and transport costs.
If suitable domestic coal is insufficient,
procurement from another source may be justified. But the decision should
follow a transparent comparison of delivered cost, quality, availability and
reliability. A proposal, an approved tender, an awarded contract and an actual
shipment are different stages and must not be conflated.
5. The financial dimension
SCCL’s February 2026 report recorded
provisional outstanding coal-supply dues attributed to TGGENCO of ₹19,733.71
crore as of 28 February. The report discusses disputed amounts and accounting
treatment that require reconciliation. The balance should not be read as
entirely overdue, undisputed or immediately recoverable.
The scale of the reported balance
nevertheless raises questions about payment discipline, dispute resolution and
the financial relationship between the coal supplier and the power utility. The
next step is to establish how much is disputed, how much has since been
collected, and how the amounts appear in audited financial statements.
What the records establish—and what they do not
|
Documented lead |
What it supports |
What it does not prove |
|
Production fell
to 58 Mt in FY2025–26 |
A sharp
year-on-year decline |
The reason for
the entire decline |
|
February report cites contractor and award delays |
Operational delays contributed to reported February
loss |
Contractors alone caused the annual shortfall |
|
CAG identified
historical contract weaknesses |
Need to examine
corrective action |
Historical
findings caused current events |
|
Naini production was far below target |
A major gap between target and output |
Transport was the sole cause |
|
Yadadri off-take
was below cumulative target |
A
supply-planning question |
An equivalent
fuel shortage at the plant |
|
TGGENCO dues were reported outstanding |
Need to reconcile payments and disputes |
The entire balance is overdue or unrecoverable |
The questions Telangana should answer
·
Why did SCCL’s production fall
in 2025–26, supported by mine-wise data?
·
What action was taken against
contractors cited in the February 2026 report?
·
What explains Naini’s
production shortfall, and when can it contribute meaningfully to supply?
·
What technical and financial
analysis supports the coal-sourcing strategy for Yadadri?
·
What is the current position of
coal-supply dues, including collections, disputes and impairments?
·
Have domestic supply, Naini
logistics and alternative sourcing been compared on a consistent delivered-cost
basis?
Biz Masala’s conclusion
Telangana’s coal problem should not be
reduced to a political contest over who is responsible. The more consequential
issue is whether mining, transport and electricity-supply systems are working
together efficiently—and whether decisions involving public money are supported
by transparent, comparable cost calculations.
SCCL’s own reports document missed targets
and operational constraints. The CAG’s earlier audit identifies specific
weaknesses in contract management and transportation-cost calculations. Naini’s
production shortfall and Yadadri’s coal off-take add further questions. These
facts do not establish that one problem caused all the others, nor do they
prove wrongdoing in any proposed procurement.
The
ultimate test is simple: before Telangana commits
more public money to securing coal, can it demonstrate what went wrong, what
has been corrected, which domestic alternatives are genuinely available, and
why the chosen option offers the best value for electricity consumers?
Sources & editorial verification notes
·
SCCL, February 2026 Performance
Report — https://scclmines.com/scclnew/arti.asp?rt=174.PDF
·
CAG Telangana, Report No. 4 of
2025 — https://cag.gov.in/ag/telangana/en/audit-report/details/124978
·
CAG full report PDF —
https://cag.gov.in/webroot/uploads/download_audit_report/2023/01.-Report-of-the-CAG-on-SPSEs-for-the-period-ended-March-2023-069ca0776bea8b5.94542484.pdf
·
Ministry of Coal, Annual Report
2025–26 —
https://coal.nic.in/sites/default/files/2026-02/chap1AnnualReport2026en.pdf
·
SCCL official production
statistics — https://scclmines.com/scclnew/performance_production.asp
·
SCCL production reporting
portal — https://scclmines.com/scclrep/prodn/default.aspx
·
Telangana government energy
review statement — https://www.telangana.gov.in/news/press-releases/2026/09/
Editorial note: Figures are attributed to
the cited official records and should be read with their stated reporting
periods and definitions. The apparent inconsistency in the Naini production
figures is expressly flagged for reconciliation. This story does not allege a
scam or establish wrongdoing. Images are AI-generated editorial illustrations,
not documentary photographs. The analysis distinguishes reported facts from
questions that the public record does not yet resolve.