ANANT RAJ: THE ₹29,500-CRORE DATA-CENTRE AMBITION
BIZ MASALA |
INVESTIGATIVE FEATURE
Financial muscle, market expectations and the Andhra execution question
Three years
of rising revenue and profits, a major equity fund-raise and an expanding
data-centre business have strengthened Anant Raj’s position. But can financial
capacity, cash generation and project execution keep pace with its ambitions?

The Andhra Pradesh MoU signing at the CII
Partnership Summit 2025. The agreement announced a proposed ₹4,500-crore
data-centre and IT Park investment.
By Biz Masala | Investigative Business Desk
The scale of the promise
Anant Raj Limited is positioning itself for
a much larger role in India’s digital infrastructure market. Its announcements
in Andhra Pradesh and Haryana together represent a proposed investment pipeline
of approximately ₹29,500 crore.
The first major commitment came on 14
November 2025. Anant Raj Cloud Private Limited, a wholly owned subsidiary of
Anant Raj Limited, signed a Memorandum of Understanding with the Andhra Pradesh
Economic Development Board (APEDB) for a proposed data-centre-cum-IT Park in
the state.
The company disclosed a proposed investment
of approximately ₹4,500 crore, to be implemented in two phases. The project was
expected to create around 8,500 direct and 7,500 indirect jobs. The MoU signing
took place in the presence of Andhra Pradesh IT Minister Nara Lokesh.
The second announcement came in June 2026.
Anant Raj announced a proposed investment of approximately ₹25,000 crore in
data centres and cloud services in Haryana.
These are proposed investment plans—not proof that the
entire amount has already been spent, financed or converted into operational
assets.
Andhra Pradesh: Amravati is identified. Execution
milestones remain the test.
The Andhra project has not disappeared from
the company’s public disclosures. Anant Raj’s FY26 annual report identifies
Amravati as the proposed location and describes a planned 50 MW IT-load data
centre alongside a 7.5-lakh-square-foot IT Park.
That is a meaningful detail. It corrects
the impression that the company has never identified a location. However, the
public material reviewed for this article does not establish a specific land
parcel and its allotment status, a construction commencement date,
project-financing milestones or a phase-wise commissioning timetable.

Andhra Pradesh Secretariat. The government’s
facilitation role and the project’s implementation milestones are distinct
matters.
The original exchange disclosure described
APEDB’s role as facilitating necessary support and coordinating with the Union
Government, if required. That wording should not be interpreted as evidence
that the government has guaranteed land, power or project financing.
Nearly a year after the MoU, the questions
for the company and the state government are practical:
·
Has a specific parcel of land
been identified and formally allotted?
·
Have the required land-use,
building and environmental permissions been obtained?
·
What is the expected
construction start date and phase-wise commissioning schedule?
·
What power capacity, redundancy
and connectivity arrangements are being planned?
·
What is the expected date for
the first phase to become operational?
The absence of a public answer to these
questions is not proof that no work has taken place. It does, however, leave
investors and the public without a clear way to measure progress against the
original announcement.
Haryana: an operating base and a much larger expansion
plan
Unlike the Andhra proposal, Anant Raj’s
data-centre business already has an operating footprint in Haryana, including
facilities at Manesar and Panchkula. Company disclosures have described
operational capacity at these locations.
In February 2026, Anant Raj Cloud announced
a strategic collaboration with Spain-based Submer Technologies to develop
AI-ready data centres. The collaboration focuses on high-density computing
infrastructure and liquid-cooling technology, with initial deployments
associated with Manesar and Panchkula.
The June 2026 Haryana proposal, with its
stated ₹25,000-crore investment, takes the ambition to a different scale. It
signals an intention to expand from existing facilities into a much larger
data-centre and cloud-services platform. The announcement alone does not
provide a complete project-by-project funding schedule, construction calendar
or commissioning timetable.

Anant Raj corporate building image supplied for
this story. It is not represented as a data-centre facility.
Three years of financial performance: the company is
growing
The financial record provides an important
starting point for evaluating the ambition. The following figures are drawn
from the company’s consolidated annual-report disclosures and are rounded to
the nearest crore.
|
Financial year |
Revenue from operations |
Total income |
Profit available for appropriation |
|
FY24 |
₹1,483.30 cr |
₹1,520.74 cr |
₹265.93 cr |
|
FY25 |
₹2,059.97 cr |
₹2,100.28 cr |
₹425.82 cr |
|
FY26 |
₹2,511.60 cr |
₹2,579.08 cr |
₹557.02 cr |

Consolidated revenue and profit trend. Profit
measure shown is net profit available for appropriation, not an EBITDA measure.
Revenue from operations rose by
approximately 69% between FY24 and FY26. FY26 revenue increased by about 21.9%
over FY25, while profit available for appropriation rose by approximately
30.8%.
This is a strong growth record. It should
not, however, be mistaken for proof that the company can immediately fund
₹29,500 crore of new investment from internal resources. The scale of the
proposed programme must be assessed against cash flows, existing commitments,
infrastructure costs and the time required for new facilities to generate
revenue.
The cash-flow question: profit is not the same as cash in
the bank
One of the most important figures in the
FY26 financial statements is not the profit number. It is operating cash flow.
Anant Raj reported approximately ₹557 crore
in consolidated profit available for appropriation in FY26. Yet its
consolidated cash-flow statement recorded negative cash flow from operating
activities of approximately ₹435 crore.
A company can report accounting profits
while cash is absorbed by working-capital requirements, receivables, advances
and other operating movements. In FY26, movements in other financial assets,
other assets, receivables and liabilities were significant.
The company also raised approximately
₹1,100 crore through a qualified institutional placement (QIP) during FY26.
This provided a substantial source of equity capital and demonstrates access to
the capital market. But equity raised is not the same as recurring cash
generated by operations.
The FY26 consolidated balance sheet
reported borrowings of approximately ₹606 crore and cash and cash equivalents
of approximately ₹911 crore. These figures are a snapshot, and should be read
alongside working-capital requirements, capital expenditure plans and the
timing of future project payments.
The
central financial question is not simply whether Anant Raj is profitable or has
cash on its balance sheet. It is whether operating cash generation, fresh
equity, borrowing capacity and project-level funding arrangements can support a
multi-year investment programme of this scale.
The market’s response: announcements and share-price
expectations
The share price is another part of the
story, but it needs to be handled with care. A stock’s movement around an
announcement is not proof that the announcement alone caused the movement.
Broader market conditions, quarterly results, valuations, liquidity and sector
sentiment also matter.
|
Period |
Indicative share-price reference |
|
October 2025
monthly close |
₹644.40 |
|
November 2025
monthly close |
₹576.45 |
|
December 2025
monthly close |
₹547.30 |
|
May 2026 monthly
close |
₹514.15 |
|
1 June 2026
close |
₹538.65 |
|
2 June 2026
close |
₹552.20 |
|
June 2026
monthly close |
₹521.25 |
|
6 November 2026
close |
₹445.45 |
The June announcement coincided with a
positive trading session: the share closed at ₹538.65 on 1 June and ₹552.20 on
2 June 2026, a rise of approximately 2.5%, after touching an intraday high of
₹563.25. The longer price path, however, shows that investors do not value
announcements in isolation.
These figures are a broad historical
snapshot, not a daily event-study chart. The November 2025 monthly close must
not be presented as the precise closing price on the MoU date. A final
event-study graphic should use verified daily NSE prices around each
announcement and compare them with an appropriate benchmark such as the Nifty
Realty index.

Illustrative market-themed image supplied for
the story; it is not an actual price chart or evidence of share-price
performance.
The proposed demerger: a new structure for the digital
business
Anant Raj has also moved towards
restructuring its businesses. The board approved a composite scheme in July
2026 to reorganise its real-estate and data-centre/cloud businesses, with the
proposed digital-infrastructure business to be housed in a separate entity,
Ashok Cloud.
The proposal remains subject to applicable
regulatory and shareholder approvals. It should not be described as a completed
demerger.
The proposed separation could give
investors a clearer view of the economics of the data-centre business: its
assets, revenue, capital requirements, liabilities and growth prospects. The
value of that exercise will depend on the details that emerge through the
formal scheme process.
Investors will need to examine the assets
and liabilities being transferred, the capital structure of the resulting
entity, the treatment of existing contracts and the funding arrangements for
expansion.
The questions Andhra Pradesh should answer
The Andhra MoU was signed in the presence
of the state’s IT Minister and presented as a significant investment
opportunity. The government’s role, as described in the original exchange
disclosure, was to facilitate support and coordination. That makes public
accountability a shared responsibility.
The state government should clarify what
facilitation has been provided since November 2025, whether land has been
identified or allotted, what approvals have been sought or granted, and whether
any infrastructure dependencies remain unresolved.
The company, in turn, should provide a more
detailed implementation update: the proposed land parcel, project approvals,
construction timetable, capital deployment plan, phase-wise capacity and
expected date of first operations.
These are not hostile questions. They are
the normal questions that follow a large public investment
announcement—particularly one carrying an employment projection of 16,000
direct and indirect jobs.
The larger test: ambition versus execution
Anant Raj has a credible starting platform:
a growing real-estate business, operating data-centre facilities in Haryana, a
partnership focused on AI-ready infrastructure, rising consolidated revenue and
profits, and access to equity capital through a QIP.
At the same time, the financial record
raises questions that cannot be answered by profit growth alone. FY26’s
negative operating cash flow, the scale of the proposed investment pipeline and
the need for project-specific funding make execution discipline critical.
The combined ₹29,500-crore announcements
should therefore be seen as a long-term ambition and proposed investment
pipeline, not as an already-funded programme or an immediate financial
obligation.
The question is no
longer merely whether Anant Raj wants to invest ₹4,500 crore in Andhra Pradesh.
The larger question is whether the company can convert its ₹29,500-crore
data-centre ambition into funded, commissioned and revenue-generating
infrastructure—without allowing the scale of its announcements to outrun the
evidence of execution.
Biz Masala will continue to track the
project’s land and approval status, construction milestones, funding
disclosures, operating capacity and the proposed corporate restructuring.
Latest operating update: H1 FY27
The company’s 28 October 2026 results
provide a more recent snapshot than the FY26 annual report. For the quarter
ended September 2026, Anant Raj reported consolidated revenue from operations
of approximately ₹661.53 crore and profit after tax of approximately ₹156.49
crore. For the first half of FY27, revenue from operations was approximately
₹1,292.93 crore and PAT was approximately ₹305.68 crore.
The Q2 FY27 business update also reported
₹115.41 crore in data-centre, infrastructure and allied-services revenue for
the quarter. The company’s stated capacity roadmap includes 63 MW by the end of
FY27 and a longer-term target of 357 MW by FY31–32.
These figures strengthen the case that the
data-centre business is becoming a more meaningful contributor. But capacity
targets are not the same as commissioned capacity, and revenue from data-centre
and allied services should not automatically be treated as revenue from fully
operational data-centre IT load.
Source and methodology note
This article is based on Anant Raj
Limited’s FY24, FY25 and FY26 annual reports, investor presentations and
exchange disclosures, together with the company’s FY27 quarterly results and
publicly available historical share-price references. Figures are rounded where
indicated. The article distinguishes announced investment proposals from
expenditure, financing and operational commissioning.
Financial figures are consolidated unless
explicitly stated otherwise. The FY26 profit figure used in the three-year
comparison is net profit available for appropriation as reported in the
directors’ report; it should not be confused with profit before associate and
non-controlling-interest adjustments. The FY26 operating cash-flow figure is
taken from the consolidated cash-flow statement.
Share-price references are indicative
historical observations and are not a substitute for a verified daily
exchange-data event study. No causal relationship between an announcement and a
share-price movement is asserted.
Photographs supplied for this article are used as contextual editorial images. The corporate building and residential-estate images are not represented as data-centre facilities. The market-themed graphic is illustrative and is not presented as market data.