Waaree’s Kakinada Leap: From Solar Panels to Green Ammonia
BIZ MASALA
| ENERGY & CORPORATE STRATEGY
A ₹15,000-crore proposal puts the solar manufacturer’s next growth chapter against a tougher test of capital, margins and export economics.
By Murthy ASR

An illustrative visual of a coastal
green-ammonia export complex; not a photograph or rendering of Waaree’s
proposed Kakinada site.
|
THE CENTRAL QUESTION |
A ₹15,000-crore proposal at the port
Waaree Clean Energy is reported to have
acquired about 300 acres in Kakinada Special Economic Zone for a proposed
green-ammonia plant with annual capacity of 1.2 million tonnes and an
investment of approximately ₹15,000 crore. The site is near Kakinada Gateway
Port, a strategic advantage for a product expected to serve export markets. The
Andhra Pradesh government has approved the proposal under its Integrated Clean
Energy Policy, 2024; a formal MoU is expected at the state’s investment summit
later this week.
The status needs precise wording. As of 10
November 2026, the public report describes an approved proposal and an MoU
still to be signed. It is not evidence that the entire project has reached
financial closure, secured binding offtake, completed all statutory clearances
or begun construction. Those milestones will determine whether the headline
investment becomes an operating industrial asset.
The strategic logic: move beyond the module
Waaree’s corporate history is built around
reinvention. The group began in instrumentation and pressure-gauge trading in
1989, moved into manufacturing, and entered solar module production in 2007.
Founder Hitesh Doshi has described how exposure to solar at a German exhibition
helped shape the shift. The instrumentation business was sold to Switzerland’s
Baumer in 2011, freeing the group to concentrate on solar.
The next stage has been deeper integration
and a broader clean-energy portfolio. Waaree has outlined a 10 GW
ingot-and-wafer complex at Nagpur with an investment of about ₹6,200 crore, a 1
GW electrolyser facility at Dungri in Gujarat with planned investment of about
₹676 crore, and a 2,500-tonne-per-day solar-glass facility with proposed capex
of ₹3,900 crore. Its May 2026 investor presentation cited ₹444 crore of
electrolyser PLI support and a separate ₹510 crore incentive for green-hydrogen
production. These are distinct incentive components, not one combined
electrolyser grant.
The Kakinada project extends that strategy
downstream: from manufacturing equipment used to generate renewable power,
towards converting renewable electricity into hydrogen and then ammonia. But
this is a different business. It requires not only manufacturing scale, but
also low-cost power, water, electrolysis, ammonia synthesis, storage,
certification, shipping and long-term buyers.
FY26 was exceptional. Q2 FY27 shows the margin challenge
Waaree’s FY26 consolidated revenue from
operations rose 83.72% to ₹26,536.77 crore. Operating EBITDA increased 117.10%
to ₹5,608.64 crore, while profit after tax rose 101.45% to ₹3,884.15 crore.
Annual module production reached 12.6 GW. These results established a strong
base, but the latest quarter shows why investors are looking beyond revenue
growth.
In Q2 FY27, revenue rose 23.9% year on year
to ₹7,517.7 crore. Operating EBITDA fell 5.1% to ₹1,335.2 crore, and the
operating EBITDA margin contracted to 17.8% from 23.2%. Consolidated PAT
declined 14.2% to ₹753.6 crore. For H1 FY27, revenue was ₹15,449.5 crore, up
47.3%; operating EBITDA rose 15.5% to ₹2,775.1 crore; and PAT was ₹1,645.5
crore, marginally below the year-earlier period.
The export mix is the sharpest warning.
Management said revenue from exports shipped from India fell to ₹89 crore in Q2
FY27 from ₹2,143 crore a year earlier, while revenue from US domestic
manufacturing rose to ₹1,300 crore from ₹732 crore. The company attributed the
export disruption to US Section 232-related uncertainty and rationalised a
significant portion of export orders. This is not the disappearance of all
overseas business: it is a shift in where products are manufactured and sold,
with implications for margins, capacity utilisation and capital deployment.
The market is marking execution risk
On 9 November 2026, Waaree Energies closed
at ₹2,444 on the NSE. Business Standard reported an all-time high of ₹3,864.40
on 12 September 2025 and a 52-week range of ₹2,162 to ₹3,556.10. The November 9
close was therefore about 36.7% below the all-time high—not the roughly 30%
implied by the ₹2,625 closing price in the original draft.
The stock price is not proof that investors
have rejected the ammonia proposal. It reflects a range of factors, including
earnings expectations, policy and tariff exposure, valuation, order conversion
and execution across several capital-intensive projects. The more defensible
interpretation is that the market is demanding evidence that capacity expansion
can translate into cash generation and sustainable margins.
Kakinada is becoming a cluster—and competition is part of
the story
The location has strategic potential, but
Waaree will not be building in isolation. The Asian Development Bank’s August
2026 project documentation describes a separate AM Green green-ammonia
development at Kakinada, planned at approximately 1.09 million tonnes per annum
in two phases. The presence of another world-scale proposal could help create
shared supply chains, port services, skilled labour and an export ecosystem. It
also raises questions about renewable-power availability, water, port capacity,
storage, certification infrastructure and competition for customers.
Europe’s carbon rules may support demand
for lower-carbon industrial inputs, but the policy signal should not be
oversimplified. The EU Carbon Border Adjustment Mechanism entered its
definitive regime on 1 January 2026 and covers fertilisers and hydrogen
production among other sectors. This is not an automatic purchase guarantee for
green ammonia. Buyers will still assess the product’s verified emissions
intensity, certification, delivered cost, contract reliability and the
applicable product rules.
The four tests that will decide whether the project works
First, power and water. Green ammonia is
only as green—and as competitive—as the renewable electricity and water supply
behind its hydrogen. Waaree must show how it will secure reliable power at a
price that supports round-the-clock plant economics, and disclose the water
source, treatment and recycling plan.
Second, offtake and logistics. Port
proximity is an advantage, not a business model. The project needs binding
buyers, credible export contracts, storage and loading arrangements, and
clarity on whether the target markets will pay a premium for certified
low-carbon ammonia.
Third, capital allocation. Waaree has
several major projects under execution or planning. Its Q2 FY27 presentation
showed net cash of about ₹3,234 crore and an order book of approximately
₹59,200 crore, but an order book is not cash in the bank and net cash does not
by itself finance a ₹15,000-crore project. Investors will need a clear funding
mix, project phasing, debt plan, partner structure and expected return profile.
Fourth, delivery discipline. Management
reiterated FY27 operating EBITDA guidance of ₹7,000–7,700 crore and indicated
that H2 would need to contribute a larger share of the annual target. At the
same time, solar-cell, wafer, glass and US manufacturing plans are competing
for management attention and capital. The question is not simply whether Waaree
can announce a new business, but whether it can execute several complex
businesses without weakening returns in its core franchise.
A new chapter—but not yet a proven escape
Waaree’s earlier move from instruments to
solar was a strategic transformation within manufacturing. The Kakinada
proposal is a larger leap into a policy-shaped, export-dependent commodity
whose economics depend on energy prices, infrastructure, certification and
long-term buyers. Vertical integration may create advantages, but it cannot
remove market risk.
For Andhra Pradesh, the project could
strengthen Kakinada’s emergence as a clean-energy export hub. For Waaree, it
could open a new growth engine beyond solar modules. But the investment should
be judged by the milestones that follow: a signed MoU, disclosed project
structure, environmental and water approvals, renewable-power arrangements,
financial closure, binding offtake and a credible construction schedule.
The solar giant has announced its next
ambition. The harder task is converting that ambition into a commercially
bankable molecule.

PROJECT SNAPSHOT | Figures reported for the
proposed Waaree Clean Energy project. They are not evidence of commissioning or
financial closure.

EARNINGS SNAPSHOT | Consolidated Q2 FY27
figures show revenue growth alongside lower operating EBITDA and PAT.

EXECUTION CHECKLIST | These are the critical
questions investors and policymakers should ask before treating the proposal as
a delivered investment.
Key numbers at a glance
|
Metric |
Figure |
Context |
|
Kakinada
proposed capex |
₹15,000 crore |
Reported
project investment |
|
Planned
ammonia capacity |
1.2 million tonnes/year |
Proposed output |
|
Land |
~300 acres |
Reported
acquisition in Kakinada SEZ |
|
FY26 revenue |
₹26,536.77 crore |
+83.72% YoY |
|
FY26
operating EBITDA |
₹5,608.64
crore |
+117.10% YoY |
|
Q2 FY27
revenue |
₹7,517.7 crore |
+23.9% YoY |
|
Q2 FY27
operating EBITDA |
₹1,335.2
crore |
−5.1% YoY;
17.8% margin |
|
Q2 FY27
consolidated PAT |
₹753.6 crore |
−14.2% YoY |
|
NSE close, 9
Nov 2026 |
₹2,444 |
~36.7% below
₹3,864.40 all-time high |